Notice of traffic and pedestrian network disruptions - September 6, 2023

Type(s)
News

15th and Foothills Intersection from Foothills and Azure to Foothills and Glenshee

  • Will be single lane and the intersection will be set to red flash, Thursday, September 7th from 9:00 am to 4:00 pm for milling and paving.
  • Emergency vehicles WILL have access.

 

2783 Vance Rd between Westwood Dr and Blakely Rd

  • Will be closed, Thursday, September 7th from 7:00 am to 3:00 pm for Utility installs.
  • Detour required.
  • Emergency vehicles will NOT have access.

 

Kavachich Rd between Bachinski Cres and Blackburn Rd N

  • Will be closed, Friday, September 8th and Saturday, September 9th from 6:30 am to 7:00 pm for paving.
  • Emergency vehicles WILL have access.

 

Bachinski Cres between Bittner Rd W and Kovachich Rd

  • Will be closed, Friday, September 8th and Saturday, September 9th from 6:30 am to 7:00 pm for paving.
  • Emergency vehicles WILL have access.

 

Bittner Rd W between Giscome Rd and Bachinksi Cres

  • Will be closed, Friday, September 8th and Saturday, September 9th from 6:30 am to 7:00 pm for paving.
  • Emergency vehicles WILL have access.

 

962 Inez Cres

  • Will have no through traffic, Friday, September 8th from 7:30 am to 5:30 pm for Shaw Cable upgrades.
  • Emergency vehicles WILL have access.

 

Gunn Rd

  • Will be single lane alternating traffic, Friday, September 1st to Friday, September 8th from 8:00 am to 4:00 pm daily for Telus utility work.
  • Emergency vehicles WILL have access.

 

Boundary Avenue between Boundary Road and Talchako Road

  • Will be closed, 24hrs, Tuesday, August 15th to Friday, September 8th for water and sewer tie-in work.
  • Emergency vehicles WILL have access.

 

 

1st Avenue and Victoria Street along 1st Avenue west of Victoria Street

  • May experience minor traffic disruptions, Wednesday, September 13th from 7:00 am to 5:30 pm for rotating pilaster on pole.
  • Emergency vehicles WILL have access.

 

University Way between Foothills Boulevard and University Way Entrance

  • Will be closed in both directions, Tuesday, August 22nd to mid October for bridge construction. Detour: Ospika Boulevard to Tyner Boulevard to University Way entrance.
  • Emergency vehicles will NOT have access.

 

Foothills Boulevard and Austin Road West

  • May experience minor traffic disruptions, Tuesday, September 26th and Wednesday, September 27th from 9:00 am to 4:30 pm for semi annual leachate force main maintenance.
  • Emergency vehicles WILL have access.

 

3rd Avenue between Vancouver Street and Brunswick Street

  • Will be closed – 24 hrs., starting, Tuesday, August 8th to Friday September 29th for watermain project.
  • Emergency vehicles will NOT have access.

 

6399 Boundary Rd

  • Will be closed, 24/7, Monday, August 21st to Saturday September 30th for install of deep utilities across boundary Rd.
  • Emergency vehicles WILL have access.

 

3rd Avenue between George Street and Queensway

  • Will be closed every Saturday starting May 6th to October 14th for the Wilson Square Community Market.
  • Emergency vehicles WILL have access.

 

Quebec St between 2nd and 3rd Ave

  • Will be closed, every Saturday in summer, from 6:30 am to 4:00 pm for the Prince George Farmers Market.
  • Emergency vehicles will NOT have access.

 

Simon Fraser Bridge

  • Southbound Simon Fraser Bridge will remain closed until October 30th, 2023. Northbound Simon Fraser Bridge will be reduced to single lane in each direction.
  • Emergency vehicles WILL have access.